Construction update

Aquella

Phuket, Thailand

Register interest property page
linkedin facebook Instagram

Start

2019
Ground Breaking

Ground Breaking

Aquella construction started with access roads and entry gates, golf course and show villa works commencing

Shovel
2019
Aug 2019
Main Entrance

Main Entrance

Main entrance to the Aquella Resort completed

Bricks
Aug 2019
August 2019
Show Villa

Show Villa

Show Villa and Sales Gallery completed within 10 month construction period

Champagne
August 2019
Q1 2021
Golf Course and Clubhouse

Golf Course and Clubhouse

18 hole golf course, driving range and clubhouse - works ongoing with the first 9 holes now completed and full completion due in Q1 2021. Country Club and 18 hole Mini Golf due for completion mid 2021

Landscaping
Q1 2021
Q4 2021
Private Villas: Phase 1

Private Villas: Phase 1

Owners villas will be completed 12-18 months from initial commitment. 

Calendar
Q4 2021