Construction update

Amber Kampot

Kampot, Cambodia

Register interest property page
linkedin facebook Instagram

Start

March 2019
Ground Breaking

Ground Breaking

With the access road works ongoing, ground breaking has now commenced 

Shovel
March 2019
July 2019
Infrastructure

Infrastructure

Drainage and Sewer installation works completed reveraling the ouline of the development footprint

Cement_truck
July 2019
Sept 2019
Groundworks complete

Groundworks complete

Facility substructure and groundworks completing. Villa substructure works almost complete and block cement fabrication in progress

Drill
Sept 2019
Nov 2019
Show Villa

Show Villa

Show villa construction now complete with ongoing interior works

Bricks
Nov 2019
Q3 2020
Completion

Completion

The development was completed in 2020 and is now open 

Completion
Q3 2020